Gen Fyansford
Supporting local Indigenous youth to experience soccer
Key Achievement
Large volume of work and diversity of workExisting waterwayEnvironmental measures10km of pipework laid.
-
LocationGeelong Region
-
ClientWinslow
-
Industry Sectors ChecklistResidential
-
Water AuthorityBarwon Water
-
Timing4 years - current
Successfully delivered 7 stages over 3 years and continuing.
Works include:
- 6.1+kms sewer pipelines and 5.2+kms water pipelines
- Large diamter pipes from 63mm to 375mm
- 7m deep Pump station with 2 no. 130kL storage tanks 19m long.
- 500+m of sewer rising mains
- Pressure Reducing Valve Station
- Large equipment used
- Included crossing of a creek Moorabool River